SMITH
![SMITH](http://gibsonhomesinc.com/wp-content/uploads/2017/01/16357983_927508948014_1845892345_o-1024x817.jpg)
SMITH
House is wrapped in Tyvek and trusses are getting set today:
![SMITH](http://gibsonhomesinc.com/wp-content/uploads/2017/01/20170120_092308-1024x587.jpg)
SMITH
Exterior walls going up and getting sheeting:
![SMITH](http://gibsonhomesinc.com/wp-content/uploads/2016/12/20161221_094453-1024x576.jpg)
SMITH
Framing Lower Level interior walls and stairs:
![SMITH](http://gibsonhomesinc.com/wp-content/uploads/2016/12/20161207_102842-1024x576.jpg)
SMITH
Main Level floor is being sheeted today:
![SMITH](http://gibsonhomesinc.com/wp-content/uploads/2016/11/20161117_085356-1024x479.jpg)
SMITH
![SMITH](http://gibsonhomesinc.com/wp-content/uploads/2016/10/DSCN5661-1024x703.jpg)
SMITH
Site has been excavated and footings are in. A few shots of forms going up for the foundation walls: